Hi,
I know this is old, but I can't find the proper way to set up a weekly and/or bi-weekly schedule. I think I figured it out, but I would like to check it before making changes to my schedule.
I am currently using cyberjock's schedule (thank you very much) and it worked well but now I'm having issues with other work done on specific days.
Instead of specific days 1st & 15th, I would like to use First Monday, and Every Other Tuesday.
For First Monday, I was going to select, 3am, dates 1,2,3,4,5,6,7 , day Monday, months all.
For Every Other Tuesday, I was going to select, 3am, dates 1,2,3,4,5,6,7, 15,16,17,18,19,20,21, day Tuesday, months all.
Can someone verify that I am doing this correctly?
Am I correct in scheduling that everything selected must be true for the schedule to run?
Thanks