A few days ago, I started three similar cloudsync PUSH/SYNC tasks, going to a Backblaze B2 bucket. At some point they all finished, and two of them have been pushing tiny incremental updates since then. The third, though, seems to have started over from scratch or something; it's currently reporting
69.00%
753 / 914, 90.546 GiB / 130.423 GiB, 42.077 KiB/s, ETA 1w4d12h2m21s, checks: 10034 / 10034
Can anyone explain why that might've happened, or help me diagnose it, and more importantly suggest a way I might prevent it in future?
Thanks!
69.00%
753 / 914, 90.546 GiB / 130.423 GiB, 42.077 KiB/s, ETA 1w4d12h2m21s, checks: 10034 / 10034
Can anyone explain why that might've happened, or help me diagnose it, and more importantly suggest a way I might prevent it in future?
Thanks!